Setting the z-value to be used for new features

The z-value for new features can be manually defined on the Production Z Management toolbar. This allows you to assign a specific z-value to all the vertices on features you create. As needed, the z-values can be updated using the Populate Z for selected features tool.

手順:
  1. Start ArcMap.
    ヒントヒント:

    If the ArcMap - Getting Started dialog box appears, you can open a new or existing map document. You can also check the Do not show this dialog box in the future check box and click Open.

  2. If necessary, load data in the map.
  3. On the main menu, click Customize Toolbars Production Editing.
  4. On the main menu, click Customize Toolbars Production Z Management.
  5. Click the Production Start Editing button Production Start Editing on the Production Editing toolbar.
    メモメモ:

    The Manage Features and Create Attributes, Update Attributes, or Metadata Attributes windows automatically appear when you start an edit session using the Production Start Editing tool.

    ヒントヒント:

    If the Create Attributes, Update Attributes, or Metadata Attributes window does not appear when you start an edit session, click the Link Feature Manager To Attributes Window button Show/Hide Attributes on the Manage Features window.

  6. Double-click the Z text box on the Production Z Management toolbar.

    The current value is highlighted.

  7. Type the new z-value to be used in the text box.

The value is now set.


9/16/2010