010126 : The end day cannot equal the start day for multi-days.
Description
The time configuration is invalid. The start and end days must not be equal.
Solution
For multiday analysis, the interval must be at least 1 day to a maximum of 365 days (366 for a leap year). The days can overlap into the upcoming year. For example, the start day could be Dec 31st and the end day Jan 5 (Julian day 365 - 5).